Contents:
- Purpose
- Scope
- Procedure
- Acceptance criteria
4.1.General Definition
4.1.1. Distribution Boards
4.1.2. Outlet
4.1.3. Over Current Protection Device
4.1.4. Circuit Breaker
4.1.5. Fuse
4.2.Reference
- Checklist for
M.D.Bs
- Responsibility
1.
Purpose: The
purpose of this standard is to provide inspection and testing procedures and
practices for to determine the safety of installed electrical system within and
associated with in industrial places or other Places where many people perform
their duties or where people live.
2.
Scope:
This standard
provides criteria for identification of hazardous condition of electrical system
in industrial places (where many people perform their duties or where people
live). Because a lot of people work in the textile mills there’s always a risk of
life and property loss.
3. Procedure:
For Electrical Inspection of the Main Distribution Board. Responsible personnel
should have complete electric tools kit and wearing safety equipment like
Gloves Helmet, and safety shoes.
Steps for electrical inspection are described below.
- Switch off the supply feeding MDB, use LOTO (Lock out, Tag
out) technique.
- Check that, the rubber mat is intact (no cracks), and is of
appropriate size.
- Check that, the MDB is clean and no fluff or dirt is
there.
- Check that the distance (clearance) of at least one meter
in front the main distribution board with the measurement tapes.
- Ensure the bus-bar of appropriate size is installed in
MDB. The thump rule for bus-bar size is
Bus-bar Size = Area of Bus-bar (mm) = 2* (Breaker
Capacity)
- Check the ampere meter and volt meter or energy flow
analyzer installed at the front door of main distribution board are working
properly. If the answer not, then repair or replace those meters.
- Check all four types of sheets on main distribution board
including D.B address, Appliances connected list, over current Devices
List, and SLD (single line diagram) also check for safety signs and
artificial respiration signs.
- Check the breaker inside the main distribution board to
see if there’s any sign of burns due to overload on the breaker. If the
signs of burning or overheating present, replace that breaker.
- Check the cable size to see if they are installed
according to the load capacity of the breakers in the main distribution
board. (No breaker should be more the load capacity of the cable). Adjust
the breaker whose capacity is higher than the load capacity of the cable.
- Check the earth cable inside the main distribution board
to see it is installed according to the size of the main cable. The thumb
rule is
Earth Cable Size = 1/2 (Main Cable Size)
- Inside the main
distribution board the phase separators between the MCCBs terminals are
installed or not. If not, inform the In charge, and install the new Phase
separators (First switch off the supply of that breaker).
- Check pair segregation. If there’s need any changing,
adopt that changing.
- Ensure that, wire lugs are being used for the cables
connection. If any cable has no wire lug, provide the wire lug.
- Ensure that, every Glands or any hole of the MDB is filled
with Sealant Foam or glass wool.
- Check that the main distribution board protection sheet to
see that it is placed in front of the bus bar or not. If not, adopt the
change according to situation.
- Ensure that the color coding is maintained in MDB.
- Check that the main distribution board indication lights
are working or not. If not replace or repair that Light.
- Check that the lock of the door is operational or not, if
not replace or repair that lock.
- Ensure no multi-looping inside the breakers terminals in
MDB. If there’s any multi-looping install new circuit, to avoid ensure no
multi-looping agenda.
- Check the location of the main distribution board, it
should be located 2.5 meter away from the washing area. In case of
non-compliance to this point, relocate the MDB.
- Check the breakers output supply to see they were working
properly, by turning breakers ON & OFF with the phase tester.
- Ensure that the CKT tags should be present. If not inform
the responsible personnel.
4.
Acceptance criteria:
- Distribution boards & Equipment shall be readily accessible.
- Distribution boards & Equipment shall not show evidence of physical damage, over heating rust, or other deterioration.
- All cables entering the equipment shall be fastened with approved connectors.
- All unused opening shall be closed using a material that meet or exceeds the wall thickness or characteristic of the Distribution boards & Equipment.
- All metal parts shall be effectively grounded or bonded using approved fitting.
- Each Disconnecting means for motors and appliances and each service, feeder, or branch circuit at the point, shall be legibly marked to indicate its purpose.
- Over Current protective devices shall be rated for the conductor under the conditions of use.
- Over Current protective devices shall not show evidence of physical damage or overheating.
- Connections and terminations of over current protective devices shall not be loose or bad.
- Listed over Current protective devices, including circuit breakers and fuses, shall be used or installed in accordance with load demand.
- Cable entering distribution boards, boxes, and devices shall be tied up and supported to ensure that stress is not transmitted to the conductors and terminations.
- The conductor size shall be not less than the ampere rating of the circuit.
- Conductor, cables, and cable assemblies shall not show evidence of overheating or burning.
- Conductor shall be terminated at distribution board, devices, and boxes to ensure a secure connection without damage to the connection or the conductor.
- More than one conductor shall not be installed in any terminal.
4.1. General Definition:
4.1.1.
Distribution boards:
A
breaker Distribution boards is an electrical box that contains one or more
circuit breakers.
An enclose channel designed expressly for holding wires, cables, or bus bars with additional functional as permitted in NFPA 70.
4.1.2. Outlet: A point on the wiring system at
which current is taken to supply utilization equipment.
4.1.3. Over current Protection
Device: A Device that automatically interrupts the circuit when current in
excess of given rating flows through the circuit because of a short circuit,
over current load, or ground fault.
4.1.4. Circuit Breaker: A device designed to open
and close a circuit by no automatic means and to open circuit automatically on
a pre-determined over current without damage to itself when properly applied
within its rating.
4.1.5. Fuse: An over current protective device containing a conductor that melts when heated by an over current condition, thus opening the circuit.
4.2.Reference: This edition of NFPA 73 standard for electrical inspection for industrial places (where many people perform their duties or where people live) was prepared by the technical committee on electrical system maintenance and released by the correlating committee on national electrical code. It was issued by the standards council on august 30, 2019 with an effective date of September 19.2019 and supersedes all previous edition.
5.
Checklist for MDB:
|
Name
of the Facility |
||||||
|
|
||||||
|
Location |
||||||
|
Checklist for MDB # _______
Located at ____________________________ |
||||||
|
Sr.# |
Items to Check |
Status |
Remarks |
|||
|
Yes |
No |
|||||
|
1 |
1 meter clearance
provided in front of D.B. |
|
|
|
||
|
2 |
Combustible material is
not stored near D.B. within 1 meter |
|
|
|
||
|
3 |
Insulated rubber mat is
provided in front of D.B. |
|
|
|
||
|
4 |
D.B. installed at
compliant location |
|
|
|
||
|
5 |
Artificial respiration installed
beside D.B. |
|
|
|
||
|
6 |
Amp, Volt meter and
Indication lights are installed & functional with protective devices/
Breaker/ Fuses |
|
|
|
||
|
7 |
Clear & Permanent
Capacity information label provided |
|
|
|
||
|
8 |
Safety sign is present on the door of D.B. |
|
|
|
||
|
9 |
D.B. has operate able door |
| ||||
|
10 |
D.B. door
and C.B. protection door is connected with Earthing |
| ||||
|
11 |
Earthing
cable size is appropriate |
| ||||
|
12 |
D.B. is
properly cleaned/concealed dust & vermin proof |
| ||||
|
13 |
Clear &
Permanent identification marking provided |
| ||||
|
14 |
Any breaker
damage |
| ||||
|
15 |
Phase separators have been installed b/w MCCB terminals | |||||
|
16 |
No circuit
is drawn without incorporated C.B. |
| ||||
|
17 |
No higher
rated C.B. against low rated cables |
| ||||
|
18 |
Wires are
separated from iron or other heat source |
| ||||
|
19 |
No undermanaged
wire found |
| ||||
|
20 |
Multi-looping
of cables is not observed |
| ||||
|
21 |
Color coding
is maintained for cables & bus bar |
| ||||
|
22 |
Each circuit
provided with dedicated neutral and earth |
| ||||
|
23 |
Presence of
Cables marking & tagging/ Wires identification i.e. CKT 1, CKT 2 |
| ||||
|
24 |
Glands/Sealant
foam/Glass wool is filled properly at top and bottom holes |
| ||||
|
25 |
Conductor is
provided with wire lugs and color insulation relevant phase |
| ||||
|
26 |
Protection
Sheet is present on Bus Bar |
| ||||
|
27 |
No
overheating, overloading & signs of burning is observed through Thermal
scanner |
| ||||
|
28 |
Earth check at equipment / appliances | |||||
|
29 |
D.B.
installed 2.5 meter away from washing area |
| ||||
6.
Responsibility:
Responsibility is imposed on the electrical engineer/Officer and the electrician who conducts the inspection, who have jointly inspected, then the Electrical Manager / HOD who will make sure that the inspection is done properly.
Reviewed by Electrical Engineering World
on
March 25, 2024
Rating:

